BRV SC 110

DEFINITION

Two component, solvent free, thixotropic epoxy light putty.

USAGE AREAS

It is used as level equalization and structural strengthening putty before laminating of composite products such as carbon black and aramid fibre in concrete columns, on underground metal and concrete pipe lines of cooling towers of power plants, at pipe joints for isolation purposes, in the restoration of historical buildings, at treatment plants, in the repair of concrete pipes, filling of corner, crack, dilatation holes, in the walls, in the ceilings, on the horizontal and vertical surfaces where chemical resistance is required. It has the ability to fill 3-4 cm deep cavities on vertical surfaces at one time.

 

Type

TS EN 1504-2/ April 2008 Principle 5(PR): 5.1 Physical Resistance / Surface Improvement Coating Application ©

Colour

Gray

Outlook

Matt

Solid Matter by Weight, %

100

Density

0,80 gr/cm³

Waste

Variable according to surface condition.

Package

15 lt  A Component + 15 lt B Component: Total 30 lt

4 lt A Component + 4 lt B Component : Total 8 lt

Flash Point

>25 °C

Mixture Ratio

1 / 1

Application Methods

Trowell, scrapper

Mixture Life

30 min/ 25 ˚C

Shelf Life

1 year

Waiting Time Between Coats

12 hours / 25 °C

Drying Time

12 hours / 25 °C

Mechanical Strength

7 days

Sanding Time

24 hours /25 °C

Equipment Cleaning

Epoxy Thinner

SURFACE PREPARATION

Free particles and paint residues on the surface must be thoroughly cleaned, surfaces should be roughened mechanically (blastrack or milling router) and cleaned from vacuum with vacuum cleaner.

MIXING PREPARATION

A and B component should be mixed with a low speed mixer for at least 3-4 minutes until a homogenous mixture is obtained by paying attention to mixture ratios.

APPLICATION CONDITIONS

* Surface should have sufficient strength. The concrete should have a compressive strength of at least 25 N/mm² and a tensile strength of at least 1,5 N/mm².

* Epoxy putty should be completed its curing before the top coat coating is started.

* Avoid application in very humid environments and below 10°C. p>* Mixing ratios should be considered.

Products that can be used under this product: When it is necessary.

* SC 210 Multipurpose Epoxy Primer

* SC 270 Low Viscosity Epoxy Impregnating Primer